Abstract
"Construction remains on schedule for an August completion of the Oakland Center expansion project. Work on the $8-million building addition began last October and is about 20 percent complete. The 30,000-square-foot addition not only will provide a distinctive architectural design as an impressive visible gateway to the university but also state-of-the-art student services."
Date
2003-03-12
Type
Other
Department
Description
News article